Formalize roles and responsibilities of PPI  | 
Q1 2011 | 
| 
Finalize draft 1.0 of zoning plan with accompanying draft regulations | 
Q1 2011 | 
| 
Solicit feedback on version 1.0 through stakeholder seminars | 
Q1&2 2011 | 
| 
Develop GIS map of target area | 
Q2 2011 | 
| 
Draft version 2.0 of zoning plan and regulations | 
Q2 2011 | 
| 
Finalize version 2.0 through stakeholder seminars | 
Q2&3 2011 | 
| 
Submit zoning regulations for passage into law | 
Q3 2011 | 
| 
Conduct zoning regulation implementation trainings The last two tasks have taken longer than envisaged. However, a draft plan is now in place, which will be forwarded for passage into law once stakeholder feedback has been incorporated. | 
Q3&4 2011 | 
Timeline
Subscribe to:
Comments (Atom)