Formalize roles and responsibilities of PPI
|
Q1 2011
|
Finalize draft 1.0 of zoning plan with accompanying draft regulations
|
Q1 2011
|
Solicit feedback on version 1.0 through stakeholder seminars
|
Q1&2 2011
|
Develop GIS map of target area
|
Q2 2011
|
Draft version 2.0 of zoning plan and regulations
|
Q2 2011
|
Finalize version 2.0 through stakeholder seminars
|
Q2&3 2011
|
Submit zoning regulations for passage into law
|
Q3 2011
|
Conduct zoning regulation implementation trainings
The last two tasks have taken longer than envisaged. However, a draft plan is now in place, which will be forwarded for passage into law once stakeholder feedback has been incorporated. |
Q3&4 2011
|
Timeline